UAT test plan template

A UAT test plan says how the people who will use the software, or who paid for it, will check that it does what was agreed: what they test, against which version of the requirements, who tests, where, when, and what counts as passing. Below is a free template, a test case and test script template with examples, entry and exit criteria, a readiness checklist, and how UAT differs from SIT and QA.

UAT exists precisely because there are things — business process nuances, legacy configurations, tribal knowledge about why the client’s data looks the way it does — that nobody but the client can fully validate.

— r/ProductManagement, September 2026

What goes in a UAT test plan

  1. What is being tested: the release, the build, and the version of the requirements it is tested against — with the change requests approved since.
  2. Scope: the business processes and requirements in, and what is out.
  3. Testers: who tests what, and who decides on defects.
  4. Schedule: when testing starts and ends, and when retests happen.
  5. Environment and data: where testing happens, and the data it needs.
  6. Entry criteria: what must be true before UAT starts.
  7. Test cases: the scenarios, linked to the requirements they check.
  8. Defects: how they are logged, ranked and decided.
  9. Exit criteria: what must be true to sign off.
  10. Sign-off: who signs, and on what.

UAT test plan template

Copy it into Word, Google Docs or Confluence. Square brackets are yours to fill in.

UAT TEST PLAN

Project:       [project name]
Release:       [release name], build [n]
Tested against: [requirements document],
               version [x.y], plus change
               requests [CR-n]
Version:       [x.y] of this plan, [date]
Owner:         [name, role]

1. SCOPE
   In:   [business processes,
         requirements]
   Out:  [what UAT does not cover, and
         why]

2. TESTERS
   [name, role]:  [processes or test
                  cases]
   Decides on defects:  [name, role]

3. SCHEDULE
   Kick-off and training: [date]
   Testing:               [date] to [date]
   Retest window:         [date] to [date]
   Sign-off by:           [date]

4. ENVIRONMENT AND DATA
   Environment:  [URL or system]
   Test data:    [what exists, who
                 prepares it]
   Access:       [accounts, roles, how to
                 get them]

5. ENTRY CRITERIA
   [ ] System and integration testing
       passed
   [ ] No open critical defects
   [ ] Environment and data ready,
       accounts working
   [ ] Test cases reviewed by the business
   [ ] Testers trained and their time
       booked

6. TEST CASES
   [link to the test case sheet]

7. DEFECTS
   Logged in:  [tool]
   Severity:   critical / high / medium /
               low
   Triage:     [who, how often]
   A request for something the
   requirements do not say is a change
   request, not a defect.

8. EXIT CRITERIA
   [ ] Every planned test case run,
       results recorded
   [ ] No open critical or high defects
   [ ] Other open defects accepted in
       writing
   [ ] Every approved change request
       tested

9. SIGN-OFF
   [name, role]:  [decision, date]

The exit criteria are what the UAT sign-off checks; that page has the sign-off document and the email that asks for it.

UAT test case template

One row per scenario, in the business’s words; the fuller format the delivery team uses is on the test case template page. It copies into Excel or Google Sheets as it is:

ID Requirement Scenario Expected result Result Tester, date
UAT-01 FR-014, FR-015 Pay an open invoice by card, as a customer’s finance clerk would The invoice shows “Paid” with today’s date; a receipt arrives by email Pass Finance clerk, 12 May
UAT-02 FR-014 Pay an invoice with a card the bank declines The invoice stays open; the bank’s reason is shown Fail — DEF-31 Finance clerk, 12 May
UAT-03 FR-011 Download last month’s invoices as PDFs Each PDF matches the invoice on screen Pass Accounts manager, 13 May

The Requirement column is what lets you say what was tested against what — and, when a requirement changes, which test cases to run again. A traceability matrix keeps that link across the project.

UAT test script template

A test script is one test case written out step by step, for a tester who has not seen the system before:

TEST SCRIPT UAT-01
Pay an open invoice by card

Requirements:  FR-014, FR-015
Tester:  [name]
Data:    test customer account A;
         invoice INV-2041, 1,250.00 EUR

1. Sign in as the finance clerk.
   Expected: the overview shows 3 open
   invoices.
2. Open INV-2041; choose "Pay by card".
   Expected: the card form shows
   1,250.00 EUR.
3. Pay with the test card ending 4242.
   Expected: "Payment received";
   INV-2041 shows "Paid".
4. Check the clerk's inbox.
   Expected: a receipt for INV-2041.

Result:  [pass / fail]
Defect:  [DEF-n]
Notes:   [   ]

Write test cases in the business’s words. A UAT test case follows a task as the user does it — “pay this month’s invoices” — not a field or a screen. Base each one on an acceptance criterion or a path through a use case, and add the cases only the business knows about: the odd customer, the month-end rush, the legacy data.

UAT entry and exit criteria

Entry criteria stop UAT from starting on software that is not ready, which wastes the testers’ time and their trust:

  • System and integration testing are complete, with results.
  • No open critical defects; the known open ones are listed.
  • The environment works, with realistic data and accounts for every tester.
  • The test cases have been reviewed by the business.
  • The testers are trained and their time is booked.

Exit criteria say when to stop and sign off — every planned case run, no open critical or high-severity defects, the rest accepted in writing. They are listed in full on the UAT sign-off page. Agree both before testing starts.

UAT process, step by step

  1. Plan: scope, testers, dates, environment — the template above.
  2. Prepare: test cases, scripts and data; accounts for every tester.
  3. Kick off: walk the testers through the system, the cases and how to log a defect.
  4. Test: testers run the cases and record results.
  5. Triage: daily, decide each defect — fix now, fix later, or not a defect. A request for something the requirements do not say is a change request.
  6. Retest the fixes, and anything they touch.
  7. Sign off when the exit criteria are met.

How long it takes varies. One team describes theirs: “We do “formal” UAT with the client at least a month before we plan to release a new feature, and we try to limit the UAT period to one week. We give them test cases and release notes to support their testing” (r/ProductManagement, 2024).

Who does UAT?

The people who will use the software, or the client who is paying for it — not the team that built it. Someone on the delivery side — a business analyst, product owner or project manager — plans it and runs the sessions.

Getting the testers to turn up is not a given. Someone who runs a product team for a large ERP described their UAT team’s job as “Facilitating a UAT where business users are encouraged to test themselves, and submit bugs. Participation has always been a big issue. Historically, my PMs have participated more than the stakeholders” (r/ProductManagement, 2024).

What helps: book the testers’ time with their managers in advance, give each one a short list of cases in their own area, and keep the window short.

UAT vs SIT vs QA

Aspect QA SIT UAT
Question Does it work as specified? Does it work with the other systems? Is it what we need, in our real work?
Who tests Testers in the delivery team Testers, with the other systems’ owners Business users or the client
Based on Requirements and technical specs Interfaces and data flows Real tasks and the agreed criteria
When During and after the build After system testing Last, before go-live
Ends with Defects fixed Systems talking Sign-off

UAT readiness checklist

  • The plan names the requirements version, with change requests, being tested.
  • Every test case points to a requirement, and every requirement in scope has a test case.
  • Entry criteria are met, and written down as met.
  • Testers are named, trained and booked; each has an account that works.
  • Test data looks like real data, including the awkward cases.
  • Everyone knows where to log a defect, and who decides on it.
  • Exit criteria and the people who sign are agreed in advance.